Utilities
Experience to match challenging demands
Valdes has established an experienced team for utility plant retrofits and upgrades. Our mix of personnel —including utilities, independent power producers, equipment manufacturers and engineering firms — allows us to approach your project with the highest degree of technical expertise and with the mindset of an owner. Valdes provides attention to detail but is also practical and cost-effective. We bring this same approach and expertise to steam production and distribution, gas storage and gate stations, renewable energy and water treatment plants.
UTILITIES PROJECT EXPERIENCE
Power Generation
Types of Power Plants:
Coal Fired Power Plants
Gas Fired Power Plants (Simple and Combined Cycle)
Biomass Fired Power Plants
Integrated Gasification Combined Cycle plants
Cogeneration Plants
Combined Heat & Power Plants
Reciprocating Engine Power Plants
Services Provided:
Conceptual Studies
Total Installed Cost Estimating
Detailed Design
Laser Scanning and Modeling
Equipment and Labor Specifications
Project Management
Construction Support
Start-up & Commissioning Support
Areas of Experience:
- Design of Site Draining, Grading, Tractwork & Storm Sewers
- Site Work
- Industrial Architectural Design for Buildings
- Structural Design
- Platform Design
- Foundation Design
- Grounding Design
- High, Medium, and Low Voltage and/or Auxiliary Power Electrical Systems
- Transformers
- DC Battery Systems
- Variable Frequency Drives (VFDs)
- Protective Relay Upgrades
- High Energy Piping (HEP)
- Material Handling Systems
- Coal
- Coal Combustion residuals
- Limestone
- Gypsum
- Boilers (Solids and Gas Fuels)
- Pressure Parts
- Burners
- Regenerative Air Pre-Heaters
- Forced Draft, Induced Draft, Primary, Secondary Fans
- Steam Coil Air Heaters
- Feedwater Heaters
- Deaerators
- Coal Mills
- Air Quality Control Systems
-
- Selective Catalytic Reducer (SCR)
- Selective Non-Catalytic Reducers (SNCR)
- Dry Sorbent Injection (DSI) Systems
- Wet ScrubbersSpray Dryer Absorbers (SDA)
- Pulse Jet Fabric Filters (Baghouse)
- Electrostatic Precipitators (ESPs)
- Turbines, Combustion and Steam and their Auxiliaries
- Circulating Water Systems
- Mechanical Cooling Towers
- Steam Surface Condensers
- Water / Wastewater Treatment Systems
- Fire Protection Design
- Balance of Plant (BOP) Systems
- Water / Waste Water Treatment
- Station and Instrument Air
- Pumps
- Cooling Water
- Pressure Vessels
- Storage Tanks
- Control System & Automation Upgrades
- DCS
- PLC
- PLC Migration to DCS
- Instrumentation
- Burner Management Systems
- Turbine Control Systems
Power Delivery Services
Substation Design
New and Upgrades
Services Provided
Conceptual Studies
Total Installed Cost Estimating
Detailed Design
Laser Scanning and Modeling
Equipment and Labor Specifications
Project Management
Construction Support
Start-Up & Commissioning Support
Areas of Experience
Relay Settings
Structural Design
Single-Line Development
Rigid Bus Design
Lightning Shielding Design
Ground Grid Design (WinIGS)
Protection and Control, AC/DC
General Arrangements
Plan and Section Drawings
Control Buildings
Raceway Design, Trenches, Duct Bank, Underground Get-Aways
Wiring Design
Laser Scanning for 3D Modeling of Substations
Lighting Design
Battery Sizing Calculations/Studies
UPS Studies and Implementation
Case Study

SALF Leachate Project
A power plant client needed to redirect ash contact water from an on-site landfill to wet scrubbers for pollution mitigation to comply with a consent degree. The client was faced with a challenge of improving existing conditions to comply with the environmental requirements agreed upon with their state government.
View More
Roof Top Solar Energy - PV Design
An international manufacturer of automotive components needed a plan for the installation of solar panels on the roof of their plant as a part of their sustainability plan. Prior to installation, various engineering services were required to properly layout the project, while technical support was needed to complete the installation prior to and during construction.
View More
480V Load Centers
A power plant had numerous 480V load centers (LCs) that had reached their end of life and most had no spare capacity. It was clear to the client that this was an undertaking that would require many years of dedicated work to evaluate the LCs and develop a plan for their replacement.
View More
Switchyard Upgrade
A client was looking to sell its trigeneration facility and required mechanical and electrical upgrades. Due to the installation of a new upstream substation, options for electrical distribution upgrades to a facility consisting of a steam plant, a chiller plant, and three generating units were necessary. They needed a report and total installed cost (TIC) estimate to approve the project.
View More
Substation Upgrade Project
A refinery client initiated a project to increase the incoming power capability from the local utility to the 34kV busses at its refinery. They needed to upgrade various aspects of its 34kV power distribution system due to the increase in available fault current and power capability provided by the new transformers (max 40MVA rating) and 138kV overhead structures and bus work.
View More
UAS Survey Mapping
A solar energy client required a solar panel design on a large rooftop. The rooftop was approximately 60 feet tall and spanned over 1,000 feet in one direction (3.5 acres) while generating 1 MW of renewable energy. The client needed an efficient and safe method of capturing the existing conditions on the roof to prepare for design work.
View More
Switchgear Replacement Study and Implementation
The units and switchgear for our client’s power plant had been in service for over 60 years, were nearing their end of life and presenting reliability concerns. Our client wanted to install upgrades to the 4kV switchgear and needed to know all of their options to get the project approved and funded.
View More
Outage Planning Services
A utility client needed to plan for an outage in their supercritical generating station. They had identified systems that were in need of replacement, including a stainless steel flue gas desulfurization (FGD) spray header system that needed to be replaced due to corrosion and failure in the existing header material, a steam chest with a substantial deformation that was resulting in operational issues with the control valves, and a degraded coal burner that was causing forced outages. Additionally, a major overhaul of the turbine of one of the units in the generating stations was due for routine service.
View MoreFull Service Project Delivery Process

Utilities
CONCEPTUAL ENGINEERING & DESIGN
Business Planning
Project Development
Project Economic Analysis
DETAIL ENGINEERING
Project Execution
Outage
PROJECT TURNOVER
Start-Up
Comissioning